| Integrity Testing - Frequently Asked Questions |
|
|
|
Below, we have tried to answer some of the most common questions visitors to this section of our website may have.
If you find that your query is not answered here, please do not hesitate to contact us by telephone or email.
Q2. Can piles be tested from cast level and, if so, what are the merits ?
Q3. Our site has a piled retaining wall. Can this be tested using 'normal' methods ? Q4. To ensure accurate analysis, do we require a specification for integrity testing ? Q5. Why don't integrity tests always penetrate throughout the entire piled length ?
Q6. Is there any general information relating to the nature of cracks within concrete piles ?
Q7. For testing, what are the minimum requirements for pile head preparation ?
Q8. Does NDTL have a Works Procedure for undertaking its pile integrity testing services ?
A1. Can piles be evaluated with their pile caps in place ?
Caps which incorporate a single pile can be evaluated, subject to certain criteria being met. If the cap is the same diameter as the underlying pile, there would be no effect on the test data. As the cap size increases, a proportionally larger amount of the downward travelling vibration wave is reflected back to the pile top. This serves to reduce the amplitude of the downward travelling vibration wave which in turn reduces the effective penetration of the tests. A cap / pile area change of about 2:1 (ie. a 600mm diameter cap on a 400mm diameter pile) would result in about half of the downward travelling vibration wave being reflected back to the pile top. A cap / pile area change of 4:1 would result in all of the vibration wave being reflected from the cap base. In this instance, no integrity assessment of the pile shaft below the cap would be possible.
For caps which incorporate multiple piles (and also ground beams), it is not possible to obtain any integrity information relating to the individual piles by undertaking the tests from the top of the cap or beam. This is because the measured data comprises the flexural response of the pile cap only.
Occasionally, piles have been exposed beneath the base of the cap and horizontal notches or ledges have been cut into the pile shaft to facilitate a test. The test data obtained under such circumstances is significantly affected by the presence of the overlying pile cap. Sample tests undertaken on sub-cap piles with notches introduced have been carried out. These indicate that the effective penetration of the tests may be as little as 2-3 pile diameters beneath notch level only.
A2. Can piles be evaluated from cast level ?
Pile integrity evaluation surveys are often specified to be undertaken from final cut off level. There are, however, some serious disadvantages associated with undertaking the integrity surveys at this late stage. N.D.Technology advocates undertaking the surveys before any excavation or trimming works have been carried out where ever possible. CFA piles, which are necessarily cast to piling platform, are particularly suitable. Pile integrity surveys from cast level have the following advantages:
1) Any pile that is more than 5 days old can be evaluated from cast level provided that the concrete at the pile top is sound. It is necessary only to clean off the pile top and no trimming is usually required. This allows a large number of piles to be tested in any one site visit which ensures that the pile integrity evaluations do not delay the site construction schedule. Further, fewer visits to a particular site can result in a significant cost saving both in terms of mobilization charges and rates per pile.
2) The quality of the test data recorded from the cast level of the pile is often superior to that available after the pile is trimmed. This is because at cast level, only a short length of reinforcing will be exposed. Resonance of the exposed reinforcing bars interfere with the measurement of the pile response.
3) In the event of a pile anomaly being identified from a cast level evaluation, there will be more time to carry out any further investigations necessary to identify the exact cause, and thus structural importance, of the feature. In this way, delays to the construction programme can be avoided.
4) Small diameter piles are susceptible to mechanical damage during excavation and, on average, approximately 3% - 5% of small diameter piles are affected. Mechanical damage usually causes very fine, horizontal fractures, usually within the uppermost 1m-2m of pile shaft and occasionally at the base of the reinforcing cage. Such fractures are rarely visible from inspection of the pile periphery and are of debatable structural importance. Mechanical damage fractures are, however, highly significant in an acoustical sense and readily apparent from integrity tests. Further, their presence precludes any integrity assessment of the underlying pile section. It is therefore necessary to expose and trim the pile to the fracture and carry out a retest.
Piles which are tested from cast level prior to excavation are less likely to have been damaged. The number of piles which require to be trimmed and retested are thus greatly reduced and the piles are evaluated 'as built'. In contrast, piles which are tested from cut off level more frequently require to be trimmed and retested. At this stage, the piles are in the critical path of the site programme and any trimming will require the piles to be rebuilt back to the required cut off level. This inevitably results in delays and associated costs to programme.
A3. Integrity tests on retaining wall piles.
The integrity evaluation of piles within retaining wall structures is undertaken in an identical manner to piles which are in complete isolation. This requires that a downward travelling vibration is introduced into the pile at head level and, if reflecting interfaces are encountered by the wave, measurement of the resulting reflections at the pile top.
If, for instance, a wall pile is of uniform section, completely isolated from adjacent piles and the toe of the pile is within the depth penetration of the test, then it would be expected to see a single reflection corresponding to the pile base within the test data. If, as is often the case, a pile is attached to its adjacent pile(s), then this attachment would represent a change (increase) in the pile properties. This in turn would cause reflection of the downward travelling vibration wave back to the pile top. The magnitude of this reflection would be dependent on the magnitude of the attachment. For example, a ‘small’ attachment over a very short distance would result in a relatively small / partial reflection of the test wave. This allows propagation of the remainder of the test wave below the attachment which in turn allows assessment of the underlying pile shaft. As the attachment becomes greater / more rigid, then a greater proportion of the test wave is reflected back to the pile top. This allows less resolution of features at deeper depths. In a worst case, complete attachment of adjacent piles prevents any assessment of the piles below the level of the attachment.
Attachment of wall piles tends to occur within soils where overbreak occurs more readily i.e. granular / fill materials. These materials tend to be at their ‘loosest’ towards piling platform level and piling contractors will ensure that greater concrete oversupply occurs within these strata. It is thus not uncommon for piles on close centres to be connected close to the pile heads. This may restrict acoustic assessment of the piles to the uppermost 1m-2m of pile shaft only. In these circumstances, visual inspection of the wall after excavation may offer more integrity information than the tests themselves.
It is sometimes commented that it may be possible to undertake evaluations prior to installation of adjacent piles. It is, however, normal practice that neighbouring piles are installed typically 1-2 days apart. Integrity evaluations should not be scheduled until the piles have achieved reasonable maturity and are at least, say, 3 days old. This dictates that adjoining piles are often installed before integrity tests can be undertaken.
A4. Should we use a specification ?
Pile integrity ‘tests’ are now required on most piling contracts. The test methods and procedures are, however, rarely specified. Consequently, integrity surveys are frequently undertaken using inappropriate testing systems which are capable only of providing minimal information regarding the integrity of the piles. Reporting can also be misleading. Facts, arising directly from the test data, and inferences are often indistinguishable and reports rarely provide the Specifier with any indication of the limitations of its conclusions or the level of assurance afforded by the pile integrity survey.
In response to requests from local authorities and several leading Consulting Engineers, NDTL has produced a model specification for the evaluation of cast in situ piles. The Specification is generic and is designed to ensure that integrity evaluation works are undertaken to a worthwhile standard.
A copy of this specification is available upon request.
A5. Why don't integrity tests always penetrate throughout the entire piled length ?
All pile integrity evaluations are subject to a finite depth penetration. This is a physical limitation.
Testing systems which utilise signal processing techniques such as ensemble averaging, auto correlation or cross spectral averaging to improve the signal-to-noise ratio of the measurement can resolve fainter reflections than systems which rely on inspection of the raw signal data only.
The same rules apply for piles which contain relative reductions in their properties.
A6. Is there any general information regarding the nature of cracks within concrete piles ?
Cracks within small diameter piles are a common occurrence. Typically 5% of all piles evaluated contain cracks / fractures. Normal causes of fractures are:
Soil surcharge normally results in cracking 1m-2m below the base of the excavation and often coincident with the base of the reinforcing, if short cages have been used. Heave and thermal cracks occur at depths typically 40%-50% of the full pile depth.
A7. What are the minimum requirements for the preparation of the pile heads ?
All piles to be surveyed in any one site visit shall be prepared fully in advance in accordance with the following sub sections.
The piles may be surveyed from cast level or cut off level. For piles cast to ground level (e.g. CFA and driven cast in-situ piles) the former is recommended.
A8. Does NDTL have a Works Procedure / Method Statement for undertaking the tests ?
Yes, a copy of which is available upon request.
|